| Test Equipment
EMCPro™
1089 Offered by Thermo KeyTek
3-Terminal Bellcore GR-1089-CORE 1st
& 2nd Level Lightning Surge Tester
EMCPro™ Offered by Thermo KeyTek
Advanced, combination, low-cost EMC
immunity test system with up to 7 compliance-level capabilities for testing for
the CE Mark and Beyond
ECAT™ Offered by Thermo KeyTek
Expert Computer Aided Test system
for ESD, EFT, Surge and Dips and Interrupts testing to Bellcore, UL, IEC, ANSI,
etc. requirements.
Dips and Interrupts
Background
Dips and interrupts can occur on the AC
power mains as a result of a fault in the distribution system such as an open
circuit breaker or a sudden large load being turned on in the immediate
vicinity. A power distribution system fault can cause a switch in the
distribution grid to open and close a number of times, resulting in multiple
interrupts to electrical and electronic equipment.
Electronic products are tested for immunity to dips and interrupts to insure
their continued reliable operation if subjected to dips and/or interrupts on the
AC power mains. The European Union’s EMC Directive mandates dips and interrupts
testing for virtually all electrical and electronic products as a condition for
obtaining the CE Mark before shipping products to member states of the European
Union.
Applicable Standards
Generic Immunity Standards, Product Standards and Product
Family Standards require that dip and interrupt tests be performed in accordance
with Basic EMC Standards: IEC 61000-4-11 and EN 61000-4-11. Thermo KeyTek’s
Application Note, “EMC Standards Overview,” provides an overview of European
Standards for electromagnetic compatibility, describes how the Standards relate
to one another, and lists sources for procuring copyrighted documents.
1 IEC 61000-4-11 and EN 61000-4-11 are virtually identical
standards.
Basic EMC Standard
The Basic EMC Standard for Dips and Interrupts
defines methods of generating consistently reproducible electrical dips and
interrupts for test purposes. They specify characteristics of the AC mains to
the EUT such as peak inrush current, transition times and durations. While the
Basic EMC Standard specifies how to perform Dips and Interrupts testing, the
Generic, Product and Product Family Standards specify the test levels and
pass/fail Performance Criteria.
Test Levels
|
Standard |
Applicability |
Levels |
|
EN 50082-1 |
Generic Immunity - Residential, Commercial and Light
Industrial |
Not required |
|
EN 50082-1Draft |
Generic Immunity - Residential, Commercial and Light
Industrial |
0%, 40%, 70% & 100% |
|
EN 50082-2 |
Generic Immunity - Industrial Environment |
Not required |
|
EN 50082-2Draft |
Generic Immunity - Industrial Environment |
0%, 40%, 70% & 100% |
|
EN 55104 |
Immunity for Household Appliances, Tools and Similar
Apparatus |
0%, 40%, 70% & 100% |
Peak Inrush Current
IEC 61000-4-11 requires the simulator be capable of supplying
peak inrush currents of up to 500A for 220V to 240V mains, and up to 250A for
100V to 120V mains. Additionally, the Standard requires this capability be
measured using a bridge rectifier connected via a switch to a discharged 1700µF
capacitor. The parallel discharge resistance should be chosen to allow several
RC time constants between tests. An example in Annex A (normative) uses a 10k
ohm resistance, providing a time constant of 17 s, “...so that a wait of 1.5 to
2 minutes should be used between inrush drive capability tests.”
The test for inrush current is performed by switching the
generator from 0% to 100% at both 90Ţ and 270Ţ to insure sufficient peak inrush
current drive capability for both polarities.
Waveform Verification
IEC 61000-4-11 requires that the simulator output be verified
periodically. For Dip and Interrupt test simulators, it is necessary to verify
the voltage transition levels, transition times to 100%, and the inrush current
capability. Most modern oscilloscopes are capable of observing the voltage
levels and transition times. For verifying the inrush current, a bridge
rectifier, suitably rated 1700µF capacitor and appropriate current transformer
are required.
Rise and fall times of PQF™
simulator transitions |
|
 |
Test Execution
According to IEC 61000-4-11, tests must be performed in
compliance with the manufacturer’s test plan, which shall specify:
• Input power of the EUT
• Performance Criteria
• Operation modes of the EUT
• Test set-up description
• Type of designation of the EUT
• Information on possible connections, cables, peripherals, etc. After each
group of tests, a complete functional test must be performed.
EUT Performance Criteria
For Dip and Interrupt tests, Performance Criteria varies in some
standards depending on the duration or severity of the dip and/or interrupt.
Under some conditions, loss of function is allowed, provided that the function
is self-recoverable or can be restored by the control operations. Under less
severe conditions, degradation of performance is allowed during the test,
however, the unit must continue to operate as intended after the test. Refer to
the tables located in the Generic, Product and Product Family Standards for
specific Performance Criteria. The product cannot become unsafe under any
conditions.
Dip and Interrupt Simulators
Dip and Interrupt Simulators produced by Thermo KeyTek meet all
the simulator requirements of IEC 61000-4-11, including those for peak inrush
current. Additionally, Thermo KeyTek simulators meet the fast switching time
requirements not only to 100% as required by the standards, but from any level
to any other level.
|